Project Description
Project Name | Well Head Facilities, Gas Gathering & Injection in Lavan Island (EPC) |
Contract Number | 2-87-3959 |
Client | Iranian Offshore Oil Company (IOOC) |
Main Contractor(s) | Payandan |
Duration | 18 Months |
Start Date | Nov.2008 |
Completion Date | May 2010 |
Location | Lavan Island- Persian Gulf |
Project Description
Engineering, Procurement and Construction of:
- 2 Wellhead facilities & flares
- 20 km 8” & 6” gas pipeline from the wellheads to Salman & Reshadat power stations
- 2 Launcher & receiver stations
- Facilities of gas receiver in Salman & Reshadat power stations
- Electrical & instrument systems
- 18 km 20 kv power line from Salman Power Station to the wellheads