Project Description

            Project NameUtility Piping to Methanol (VI) Mobin Petrochemical Plant (PC)
Contract Number41-106/211
ClientMobin Petrochemical Co.
Main Contractor(s)Payandan
Duration 14 Months
Start DateFeb.2008
Completion Date Mar.2009
LocationAssaluyeh- Bushehr Province

 

Project Description

 

Procurement, Construction and Installation of piping utility to Methanol Unit (VI)

and water pump station which consist of:

  • Let down station.
  • Gas stations.
  • 16”, 20” & 24” High pressure steam piping.
  • 8” demine water piping.
  • 8” Nitrogen piping.
  • 14” & 20” High pressure oxygen piping.
  • 20” Medium pressure steam piping.
  • 12”& 4” Low pressure steam piping.
  • 16” Gas pipeline.
  • Valves, fittings, coating, painting.
  • Electrical & instrument