Project Description
Project Name | South Pars Gas Field Development- Phases 22, 23 & 24 (C) |
Contract Number | PSA-SP-PC-PAY-91-369 |
Client | Petro Sina Aria Co. |
Main Contractor(s) | Payandan |
Duration | 16 Months |
Start Date | Sep. 2012 |
Completion Date | Jan. 2014 |
Location | Assaluyeh – Bushehr Province |
Project Description | This project (Area 01) is part of South Pars Gas Field Development Phases 22, 23 & 24 in Assaluyeh. The area consists of following units: Unit 102, unit 103, unit 109, unit 110, unit 122, unit 160, unit 181 and 185. The construction work consists of installation of 3,300 tons rotary and fixed equipment, 180,000 in-dia.Piping, Painting, Insulating, Test, Pipe support installation and pre-commissioning. |