Project Description
Project Name | South Pars Gas Field Development – Phase 13 (C) |
Contract Number | 90-162 |
Client | Petro Paydar Iranian Co. |
Main Contractor(s) | Payandan |
Duration | 16 Months |
Start Date | Dec.2011 |
Completion Date | Apr.2013 |
Location | Assaluyeh – Bushehr Province |
Project Description
This project is part of South Pars Gas Field Development Phase 13 in Assaluyeh.
The area consists of 3 units and each unit includes following items:
Unit 101 for gas treating (4 trains), unit 104 for dehydration and mercury guard (4 trains), unit 105 for ethane recovery (4 trains), unit 182 and 160-k.
The construction work consists of installation of 12,000 tons rotary and fixed equipment, 550,000 in-dia. piping, and 35,000 m³ concrete works.