Project Name | Lavan Island firefighting & F&G system upgrading & Improvement (EPC) |
Contract Number | 2-92-4754 |
Client | Iranian Offshore Oil Company (IOOC) |
Main Contractor(s) | Payandan |
Duration | 18 Months |
Start Date | Sep.2014 |
Completion Date | Feb.2016 |
Location | Lavan Island- Persian Gulf |
Project Description
Engineering, Procurement and Construction of:
- Offshore water transmission pipeline (1000 m 48”)
- Seawater intake area
- Fire station area
- Water Transfer pipeline & fire water network
- Fiber Optic cable – F & G system – Safety system
- Electrical network
- New control & Substation buildings
- Fire training ground