Project Description

Project NameIraq (Abadan-Basrah) C
Contract NumberTEGI .Co/AB/C5/2015
ClientTADBIR ENERGY GOSTAR IRANIAN Co.
Main Contractor(s)Payandan
Duration 3 Months
Start DateDec.2015
Completion Date March.2016
LocationBasrah

 

Project Description

The Project includes 13Km of Pipeline including all trenching, pipe laying, welding, backfilling, post welding, hydrostatic test.