Project Description

Project Name Iraq (Abadan-Basrah) C
Contract Number TEGI .Co/AB/C5/2015
Client TADBIR ENERGY GOSTAR IRANIAN Co.
Main Contractor(s) Payandan
Duration 3 Months
Start Date Dec.2015
Completion Date March.2016
Location Basrah

 

Project Description

The Project includes 13Km of Pipeline including all trenching, pipe laying, welding, backfilling, post welding, hydrostatic test.