Project Description

 

Project NameTop Deck Installation on Pars Petrochemical Port (EPC)
Contract Number82132
ClientNational Petrochemical Company (NPC)
Main Contractor(s)Payandan
Duration 39 Months
Start DateMay 2003
Completion Date Aug.2006
LocationAssaluyeh – Bushehr Province
Project DescriptionThe objectives of project were to design, procure, construct and commission the top deck installation in order to export propane, ethylene and ammonia from nearby petrochemical plants to the 5 offshore jetties & 30 loading arms in South Pars Assaluyeh.

Main parts of the work consist of 6,000 tons pipes, 8,500 tons steel structures, 100,000 in-dia. piping, 200 km cabling for instrument and electrical system, installation of metering units and 30 loading arms with accessories.