Project Name56” Loushan- Rasht Gas Pipeline (PC)
Contract Number432373
ClientNational Iranian Gas Company (NIGC)
Main Contractor(s)Payandan
Duration 30 Months
Start DateSep.2009
Completion Date Apr.2012
LocationGilan Province

 

Project Description

This project is part of IGAT III starts from Loushan valve station for 80 km and ends at Lakan in PC bases contracted with NIGC.

Procured materials consist of 3LPE coating material, valves, fittings, heat shrinkable sleeve, cathodic protection equipment & consumable material.

Main parts of the project consist of 80  km 56” pipeline work, 1 branching station,
2 mainline valve stations, 1 receiver station, 2 C.P. stations and 2 hot-tap inter connections.