Project Description
Project Name | 56” Loushan- Rasht Gas Pipeline (PC) |
Contract Number | 432373 |
Client | National Iranian Gas Company (NIGC) |
Main Contractor(s) | Payandan |
Duration | 30 Months |
Start Date | Sep.2009 |
Completion Date | Apr.2012 |
Location | Gilan Province |
Project Description
This project is part of IGAT III starts from Loushan valve station for 80 km and ends at Lakan in PC bases contracted with NIGC.
Procured materials consist of 3LPE coating material, valves, fittings, heat shrinkable sleeve, cathodic protection equipment & consumable material.
Main parts of the project consist of 80 km 56” pipeline work, 1 branching station,